Myl Hi Plumbing and Heating

The pressure is on!

     April 21, 2015 0 Comments

We have the drywall installers scheduled to be on site in a few days so the pressure is on big time for the crews from Myl Hi Plumbing and Heating, DC-10 Systems and Automated AV to finish up their work before the walls are boarded up. No problem though for these great companies! Myl Hi Plumbing…

Plumbing & Tubs

     April 17, 2015 0 Comments

The crew from Myl Hi Plumbing and Heating was on site to begin installing water pipes! Myl Hi uses Wirsbo aquapex. Pex tubing is now used in most situations for potable (hot/cold) plumbing situations for a few reasons. Since the tubes are flexible, it can easily be run through trusses. Unlike copper pipes used in the…

Plumbing & Electrical

     March 9, 2015 0 Comments

Now that the house is officially at lock-up, work can begin on the inside! Lock-up means that the house is weather proof (ie. shingles are on, windows are in) and is now a secure building since the doors lock. There is a rather large list of things that must be completed before drywall can go…

The roof, the roof, the roof is…. closed in.

     January 27, 2015 0 Comments

What did you think I’d say? On fire? That’d be unfortunate. There’s been some great progress at the house! The roof sheathing has been nearly completed by Limitless Construction and we’ve scheduled Canridge Roofing to come in to shingle it. The arch is also well on it’s way to being complete. Things are starting to look good!…

Framing: Part 3

     December 16, 2014 0 Comments

Yesterday I went over step#1 and step #2 in the framing process. Let’s go over step #3, shall we? Step #3: Main floor interior walls Manny and his crew from Limitless Construction were on site and built the interior walls within a couple of days. The main floor interior walls need to be put up before the main floor support beam…